Punjab Works Department (B & R)
 

4-B PSRSP

SNoName of WorkLength(In Km)Estimated Cost(In Lacs)Technical No & DateTechnical Amount(In Lacs)Annual TargetDate of Start of Bituminous WorkPhysical Progress Upto the End of Previous Month (in Kms)Physical Progress During the MonthTotal Progress (in kms)Financial Progress Upto the End of Previous Month (in Lacs)Financial Progress During the MonthTotal Expenditure (in Lacs)Date of AllotmentDate of Completion As per Allotment/RevisedReason for DelayRemarks
1"Construction of Dehlon Bye Pass. Package No.PSRSP/WB/UG/2/BP/NCB2.831831.83CE/PSRSP/ No 116 date 16-02-20171831.83  100%0100%1512.980.001512.982016-12-2228/06/2017Completed 
 Total 2.831831.83 1831.83     1512.980.001512.98    