Punjab Works Department (B & R)
 

Status of Utility Shifting

Year:       Month:       Circle:      

SNoName of CircleName of the Road/BridgeLength(in Km)Project CostTechnical Sanction (No & Date)Technical Sanctioned Amount (In Lacs)Date of AllotmentTender AmountPhysical Progress (In %age)Financial ProgressTarget Date of CompletionUtility Shifting StatusRemarks
1Central Works Circle, LudhianaWidening to 2-lane with paved shoulder & stg. In Km. 48.490 to 60.860 Sultanpur Lodhi-Gidderpindi section of NH-703A in the State of Punjab12.372745.8200.0019/04/20161226.8585%1019.9718/07/2018 work in progress . Rs 8.93 crore transfer to Forest Department
2 Total12.372745.82 0.00 1226.85     