SNoCircleNameName of WorkLength(In Km)Amount(In Lacs)Technical No & DateTechnical Amount(In Lacs)Date of AllotmentTender Amount(In Lacs)Physical Progress Upto End of Previous MonthPhysical Progress During MonthPhysical Total ProgressFinancial Progress Upto End of Previous MonthFinancial Progress During MonthTotal Expd(In Lacs)Date of Completion As per Allotment/RevisedReason for DelayRemarks
1Construction Circle, LudhianaUPGRADATION OF MULLANPUR - HUMBRAN ROAD (ODR-02) FROM RD 0.00 TO 10.40. UNDER NABARD-XXIV SCHEME10.40665.00CE No.3417 dt.16.10.19660.0016/11/2018521.0098098616.000.00616.0015.05.19 31.3.20  
  Total10.40665.00 660.00 521.00   616.000.00616.00   
Latest Uploaded on 28 February