Punjab Works Department (B & R)
 

1.6.1 - PIDB Funded Plan Roads


SNoCircle NameRoad/Bridge NameLength(In Km)Administrative No/DateAdministrative Amount(In Lacs)Technical Sanction No & DateTechnical Sanction Amount(In Lacs)Date of AllotmentTender Amount(In Lacs)Physical Progress Upto End of Previous MonthPhysical Progress During MonthPhysical Total ProgressFinancial Progress Upto End of Previous MonthFinancial Progress During MonthTotal Expd(In Lacs)Date of Completion As per Allotment/RevisedReason for DelayRemarks
1Construction Circle, ChandigarhRopar Abiana Noorpur Bedi. (RD 0.00 to 12.50 Kms)12.50-1500.00CE. (South) Patiala memo No 400/PR-Marg dated 20.02-171372.0009/11/20181347.0078%0%78%709.3074.00783.3031-11-2018-* Progress slow due to Non cutting of Trees, NGT Ban & Non receipt of funds from PIDB. 9.50 Kms DBM & 8.00 Kms BC laid
  Total12.50 1500.00 1372.00 1347.00   709.3074.00783.30   