1.6.3 - Urban Mission Plan Roads


SNoCircle NameRoad/Bridge NameLength(In Km)Administrative No/DateAdministrative Amount(In Lacs)Technical Sanction No & DateTechnical Sanction Amount(In Lacs)Date of AllotmentTender Amount(In Lacs)Physical Progress Upto End of Previous MonthPhysical Progress During MonthPhysical Total ProgressFinancial Progress Upto End of Previous MonthFinancial Progress During MonthTotal Expd(In Lacs)Date of Completion As per Allotment/RevisedReason for DelayRemarks
1Construction Circle No. 2, JalandharBalachaur-Bhaddi-Nurpur Bedi road (PR)14.50 46.33 44.56 44.1280%2%82%0.000.000.0021.8.17   
  Total14.50 46.33 44.56 44.12   0.000.000.00   