SNoCircle NameDistrictPhaseName of Work/Package NoLength (In Km)Amount (In Lacs)Technical Sanction No & DateTechnical Sanction Amount (In Lacs)Physical Progress Upto End of Previous MonthPhysical Progress During MonthPhysical Total ProgressFinancial Progress Upto End of Previous MonthFinancial Progress During MonthTotal Expd (In Lacs)Date of AllotmentDate of Completion As per Allotment / RevisedReason for DelayRemarks
1Construction Circle No. 1, JalandharJalandharPeriodic Renewal of PMGSY phase-VIIIBhogpur to Jande Sarai PB-082111.20131.28CE. Central Memo No. 332/PMGSY Dt. 09.10.2019131.2895%5%100%0.000.000.0007/01/202031.08.2020LockdownWork Completed (Alloted Amount 104.70)
2Construction Circle No. 1, JalandharJalandharPeriodic Renewal of PMGSY Phase-VIIIPartapura Hardaspur (Section Salarpur to Hardaspur (Package No. PB0826)2.4628.832564 Dt. 11.10.201927.38100%0%100%0.000.000.0026/12/201930.06.2020-Work Completed
    Total13.66160.11 158.66   0.000.000.00    
Latest Uploaded on 30 September